After connecting overhead piping, the underground main may be flushed.

Prepare for the Local 483 Apprenticeship Exam. Utilize flashcards and multiple-choice questions, with hints and explanations for each. Get exam-ready today!

Multiple Choice

After connecting overhead piping, the underground main may be flushed.

Explanation:
Flushing is a commissioning step used to clear debris and air from a piping system. When overhead piping is connected to an underground main, debris from cutting, threading, or backfilling can be carried into the underground line. Flushing pushes water through the main to remove those sediments and to purge air, ensuring the line is clean and ready for testing or service. That’s why the statement is true: it may be flushed as part of proper installation and preparation, following the project specs and codes with the appropriate valves and drainage in place.

Flushing is a commissioning step used to clear debris and air from a piping system. When overhead piping is connected to an underground main, debris from cutting, threading, or backfilling can be carried into the underground line. Flushing pushes water through the main to remove those sediments and to purge air, ensuring the line is clean and ready for testing or service. That’s why the statement is true: it may be flushed as part of proper installation and preparation, following the project specs and codes with the appropriate valves and drainage in place.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy